Phase Two Subphase Two

Bondurant, Iowa April 9, 2020 - 

 

The contractor has been making some great progress on the roadway construction surrounding the Bluejay project.  As we near the next phase of construction beginning April 20th, here are the upcoming road closures and detours in the project.

 

Phase 2 of the project includes two subphases 

  • Subphase Two will reconstruct Grant St between Wolf Creek Rd and Phase One.  This section will be closed beginning April 20th and extend through August 2020.
    • Wolf Creek Rd will remain open throughout the duration of Phase 2 and serve as the primary access for residents of the Wolf Creek Neighborhood.
    • After May 20th the intersection at Grant and 32nd will fully open for traffic in all directions.