Utility Work: Partial Lane Closure 2nd St. NW- Mud Creek to Lincoln St. NE

[Bondurant, Iowa, April 2, 2021] Starting Tuesday, April 6th or Wednesday, April 7th, 2021 (Weather Permitting) utility work will begin along on 2nd St. NW from Mud Creek to Lincoln St. NE

This utility work is being done for the Mi-Fiber high-speed internet overbuild project here in Bondurant. There will be temporary lane closures in the Westbound lane of 2nd St. NW and flaggers will be controlling traffic from time to time.

This work along 2nd St. NW will take approximately 8 to 10 days (weather permitting) to complete. The contractor has agreed to avoid peak traffic flow times and work will generally occur after 8:30 am and halt before 4 or 4:30 pm.

Residents and motorists are asked to please use caution while this work is taking place. We appreciate everyone’s patience as Mi-Fiber works to provide High-speed internet service to all of Bondurant.