Phase Two Subphase One

Bondurant, Iowa April 9, 2020 - 

The contractor has been marking some great progress on the roadway construction surrounding the Bluejay project.  As we near the next phase of construction beginning April 20th, here are the upcoming road closures and detours in the project.

 

Phase 2 of the project includes two subphases 

  • Subphase One will construct the remaining section of 72nd/Grant St north of Phase 1B.  This section will close beginning April 20th and be reopened by May 20th
    • The intersection at 32nd and Grant will be open for local through traffic in the westbound to southbound and northbound to eastbound directions.
    • Concurrently to the Grant St closure, 32nd St between Wolf Creek Rd and Stage 1A will be closed for reconstruction.